Equipment for agro and timber industrial complex
13 years of experience
100 employees
+375 44 583 98 52

Fuel Pellet Production Line 2 tons/hour

Object characteristics

  • The complexity class of the object K-3 CH 3.02.07-2020.
  • Capacity: 2 t/h.
  • The diameter of the pellet is 6.0-8.0 mm.
  • The initial moisture content of the feedstock is up to 60%.
  • The degree of protection of the equipment is at least IP54...More

Technological solution

  • The building area of the main pellet plant is 1025 m2.
  • The size of the pellet shop is 57x18mx5.5 m.
  • The required capacity of the facility is up to 1370 kW.
  • Water consumption - up to 1.0 m3/day.
  • The height of the chimney is 14.067 m, diameter is 950 mm...More
Minsk region, Berezinsky district
27 months

Project stages

The beginning of work:  05.04.2021

Delivery of the project:  16.07.2023

Back to list Next project

Equipment advantages

Own production

Globalprodservice is the first manufacturer of equipment for the extrusion and processing of oilseeds in Belarus

Own production

Resource-saving technology

Our equipment allows you to minimize costs in your business due to low energy consumption, automation, high power, reliability and durability.

Resource-saving technology

Versatility

The ability to process different raw materials, optimally use the room, integrate production lines in accordance with the individual characteristics of the enterprise.

Versatility

Other projects

Fuel Pellet Production Line 2 tons/hour

Fuel Pellet Production Line 2 tons/hour
Minsk region, Kletsky district
25 months

Project stages

The beginning of work: 05.04.2021

Delivery of the project: 16.05.2023

The operating mode of the projected production is 350 days /year, 3 shifts of 8 hours each. Capacity: up to 1.5 t/h. The diameter of the pellet is 6.0 -8.0 mm. The initial moisture co... More

Fuel Pellet Production Line 3 tons/hour

Fuel Pellet Production Line 3 tons/hour
Gomel region, Petrikovsky district
11 months

Project stages

The beginning of work: 09.12.2021

Delivery of the project: 16.11.2022

The building area of the main pellet plant is 1381.38 m2. The building area of the modernized warehouse is 650 m2. The required capacity of the facility is up to 1370 kW. Water consum... More
Show more